Relocation of tanneries: how long will it take?

9 February 2016



With the slow progress of work and missed deadline to relocate Hazaribagh tanneries to Savar, Pinaki Roy examines the efforts to complete the central effluent treatment plant and more.


Although the Indian Government has set 1 March as the new deadline for moving the tanneries from the capital's Hazaribagh to Savar, not a single factory building at the new site is going to be ready for relocation by the deadline.

The central effluent treatment plant (CETP), the most essential component of the project, is not ready either. A little over 50% of the work at the plant has been completed.

Out of around 150 factories, 25-30 may be able to start operations at the tannery industrial estate in the next two months, according to project officials.

The plan to relocate tanneries to Savar was made 13 years ago to save the old Dhaka area from serious pollution, but the 'leather town' in Savar could not be completed in time as the tanners never showed any real interest in relocating their factories there. Ongoing legal tangles that have lasted for years are also partly to blame.

It wasn't until April 2013 that the design for the tannery site in Savar was approved. Since then, Bangladesh Small and Cottage Industries Corporation (BSCIC) has written to the owners at least 30 times, asking them to complete construction of the factories and move there - yet this was all in vain.

On 9 January, Industries Minister Amir Hossain Amu asked the tanners to move to Savar within 72 hours. However, following negotiations with the owners, the ministry gave them until 1 March.

"I've told them if they don't relocate by 1 March, electricity connections at Hazaribagh factories will be snapped. And it's going to happen," he says.

Nothing is ready

With only a short time to go before the deadline, no factory building is ready there. Some owners started preparing work for the construction only recently.

On a visit to the site, it was seen that most tanners have started the construction work; however, construction of only a few factories is nearing completion. Some owners just finished setting up the boundary walls and are yet to start construction of the main factory buildings. Out of approximately 150 plot owners, only about 30 have made some notable progress in setting up their establishments.

"To be frank, hardly 25 to 30 factory owners might complete their work and move their factories in the next two months. Other factories will take more time, maybe a few months, as they have just started the piling work," says Abdul Qaiyum, director of the tannery relocation project.

Also, the government is yet to provide utility services, including gas and electricity connections, there.

With regard to this, Qaiyum said he held a meeting on 30 January with the tanners and the gas and electricity authorities "so we can give the connections as soon as possible".

There are 205 plots at the tannery estate, of which 154 were allocated. Later, allocation of three were cancelled.

"At least 100 owners have completed foundation work of their factory buildings. The moulding of roofs of around 50 buildings has been done," says Moin Uddin of the BSCIC, who is in charge of the leather town.

In mid-January, he visited the site to monitor the work progress. After the survey, he made a list of 16 factories that made poor progress and warned them about it.

CETP work halfway

Though the industries minister has apparently made it his mission to relocate tanneries since he took office two years ago, the reality is that the government itself has failed to meet its own deadlines to complete the work of the CETP. The latest deadline for this was December 2015.

Though the industries minister has apparently made it his mission to relocate tanneries since he took office two years ago, the reality is that the government itself has failed to meet its own deadlines to complete the work of the CETP.

So far, two out of the plant's four units have been completed. In addition, installation of the pipelines to carry wastewater for treatment at the CETP remains unfinished. Asked about this, the minister blamed the factory owners for not building their factories despite repeated notices.

"Now we are slowing down the installation of the CETP because we need waste to check whether the plant works properly or not. If the tanners start moving, we will be able to complete the rest of the work within 15 days," he adds.

"We have constructed the tub where all the sludge will gather. After that, the wastewater will have to be treated biologically for three days to decontaminate it. We have completed two units out of the four."

Once in full operation, the CETP will be able to treat 25,000m3 of waste a day. As of now, it is ready to treat around 13,000m3. Also, the unit that will treat chrome-mixed water is yet to be completed.

"We have made a temporary arrangement for storing chrome-mixed water in a pit. Later, we will discharge it after treatment," says Professor Delowar Hossain of Buet who has been working with BSCIC as a consultant of the CETP construction.

Asked about the delay in constructing the treatment plant, the professor said Chinese company JLEPCL provided 18 containers with substandard machinery without government approval.

"We did not receive those substandard materials... We are importing new machinery and it is supposed to come in two to three weeks," he says.

"Even if we want to run the CETP on a test basis, we need at least 25 to 30 factories in operation at the Savar tannery estate. Without this, we cannot check whether the CETP works or not," he points out.

Engineer Md Ali said they had been laying around a 1,500km-long network of pipelines to connect all the factories with the CETP.

"We are done with installing half of the network. Installation of the rest is under way," he adds.

More time needed

The issue came to the spotlight again when Amir Hossain Amu instructed the BSCIC authorities on 9 January to send legal notice to tannery owners to relocate within 72 hours.

Since then, BSCIC has sent legal notices to at least 116 tanners to this effect knowing full well that none of them could meet such a short deadline.

Abu Taher, the past president of Bangladesh Finished Leather Goods Manufacturers Association, says given the realities, they needed more time.

"I think all tanners will be able to move to Savar by June this year," says Abu Taher.

"We need around Tk3,500 crore to complete the relocation work. But the government promised to give us only Tk250 crore, and we are yet to get 80% of the money. Still, the tanners are working hard to relocate from Hazaribagh."

A version of this article first appeared in India's Daily Star.

The remaining factories have just begun the work, making the tannery relocation process within the deadline uncertain.
Not a single factory building there is ready yet; only 20 to 30 plot owners have made notable progress in building factories at the site.
The current state of the ‘leather town’ in Savar; tanners located inside Dhaka city have been directed to move to the new site by 1 March.


Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.